Tottenham Hotspur FC Training Centre

Football Pitch Construction · April 2026

Tottenham Hotspur FC Training Centre

Sand Banding Phase Two

Overview

Following the success of the original sand banding installation carried out in May 2024,

Fineturf were reappointed by Tottenham Hotspur to return to pitch seven at Hotspur Way

Photography

On site at Tottenham Hotspur FC Training Centre.

12 photographs · April 2026

Training Centre and complete a second phase of works.

The 2024 project installed sand slits at 1.5m centres across the pitch. Having

demonstrated a measurable improvement in surface drainage and pitch performance, the

club took the decision to intensify the secondary drainage network by infilling between the

existing slits — effectively halving the spacing to deliver a comprehensive sand band

installation at 750mm centres across the full pitch area.

Fineturf returned in April 2026, again deploying the Shelton 710 trencher to install the new

slits at 50mm wide and 250mm deep, working precisely between the established bands to

ensure uniformity throughout the profile.

The backfill specification remained consistent with the original programme. The lower

125mm of each channel was filled with 2–6mm gravel to maximise porosity and promote

rapid downward water movement. A secondary pass then delivered 125mm of Redhill 45

sports sand into the upper portion of the channel, which was press wheeled before a final

pass topped the sand flush to a level finish.

The result is a pitch now served by a fully interlocked sand slit drainage network at 750mm

centres — a specification that delivers exceptional percolation rates and resilience against

the most sustained periods of rainfall.

As with the first phase, the Fineturf team completed the works efficiently and within the

required renovation window, handing the pitch back to the Tottenham grounds staff in

excellent condition and fully prepared for their end of season renovations.