Cyden Homes

Water Management · August 2019

Cyden Homes

Pond Construction

Overview

During this project we worked for T Balfe Construction to construct a pond as part of a new Cyden Homes development. We supplied heavy plant including Volvo EC140 excavators, Volvo A25 dumper and a Hydrema. We excavated 6000m3 of material for the lake formation and stockpiled on site. We then trimmed and shaped 6500m2 of material to construct the banks. Using the previously stockpiled topsoil we then graded a 300mm layer onto the banks.

Photography

On site at Cyden Homes.

13 photographs · August 2019