Belton Woods Golf Club and Hotel

Golf Course Construction · February 2013

Belton Woods Golf Club and Hotel

Hotel Driveway Ditch Installation

Overview

The De Vere Belton Woods Hotel driveway was flooding due to excessive run off from the hotel car park and adjoining woodland.

A new open ditch was excavated to catch water run off from the woodland and 24lm of 450mm plastic pipe installed under the driveway. A second open ditch was excavated to connect the new pipe into an existing dyke. Concrete headwalls were cast and fitted either side of the driveway along with debris and vermin guards. Finally, the driveway and kerbing stones were replaced and grass verges reinstated with topsoil and turf.

Photography

On site at Belton Woods Golf Club and Hotel.

17 photographs · February 2013

Enquire

Discuss a similar golf course construction project.